The original plan for Clane Road Works in 2020 was disrupted due to COVID-19.
This page has been updated to reflect the new schedule of works which has now been revised to an 8 week schedule.
The new schedule is as follows:
- Week commencing May 18th – 24 Hr Works on Kilcock Junction – Access to Main St. Clane via Sallins Rd & Prosperous Rd.
- Week commencing May 25th – 24 Hr Works on Ballinagappa Junction & Main St (between Millicent Junction & Prosperous Rd. Junction) & lane closure between Pump St. & Roundabout – Access to Main St. Clane via Prosperous Rd.
- Week commencing June 1st – 24 Hr Works on Ballinagappa Rd. & Main St (between Millicent Junction & Prosperous Rd. Junction) & lane closure between Pump St. & Roundabout – Access to Main St. Clane via Prosperous Rd.
- Week commencing June 8th – 24 Hr Works on Prosperous Rd. & Celbridge Rd. – Access to Main St. Clane via Kilcock Rd., Ballinagappa Rd & Sallins Rd.
- Week commencing June 15th – 24 Hr on Prosperous Rd. – Access to Main St. Clane via Celbridge Rd., Kilcock Rd., Ballinagappa Rd & Sallins Rd.
- Week commencing June 22th – 24 Hr on Prosperous Rd. – Access to Main St. Clane via Celbridge Rd., Kilcock Rd., Ballinagappa Rd & Sallins Rd.
- Week commencing June 29th – 24 Hr on Prosperous Rd. – Access to Main St. Clane via Celbridge Rd., Kilcock Rd., Ballinagappa Rd & Sallins Rd.
- Week commencing July 6th – 24 Hr on Prosperous Rd. – Access to Main St. Clane via Celbridge Rd., Kilcock Rd., Ballinagappa Rd & Sallins Rd.